This test facility is used to develop a methanation technology as a carbon recycling technology. Methane will be produced through synthesis of the CO2 generated at the Koshijihara Plant during the natural gas production process, together with hydrogen produced through electrolysis of water. Later, technical issues will be evaluated, including how to optimize the methane synthesis process, through a series of tests and continuous operation.
Poroject Lead: Hitachi Zosen Corporation
Region: Asia
Country: Japan
City/Town: Nagoka
Timeline Start - End: 2017-01-01 - 2019-01-01
Project Status: Completed
Project Budget: 11188110.0 €
Funding source: N.A.
Activities:
- CCU (Power-to-X)
CO2 Source: Thermal power plant
CCU Tecnology Category: Capture (Point sources) and Utilization
Info On Utilization:
- Thermal conversion
- Chemical conversion
Facility stage: Operational
End TRL: 7
CO2 capture/Utilization:
Production Volume:
Product Categories:
- Fuels
Specific Product(s): Methane
- Hitachi Zosen Corporation
- INPEX Corporation
- Technology Development Organization (NEDO)